Project Update: Bannister Downs Dairy Creamery

June 19, 2017

Work on site at Banister Downs new Dairy and Creamery is progressing to schedule with the key target of being weather proof ahead of the incoming winter weather in Northcliffe achieved.  Externally, work has now commenced on installing the clips for the feature anodised Façade system which envelops the front of house and car park entrance elevations which will take shape over the next few months.

Internally service pre lay and stud walling are progressing and delivery of the Process Area wall panels scheduled in the next month.  Civil work to the Automated Milking Rotary in the Dairy has commenced to achieve the long standing scheduled delivery and installation date.  With completion due in December work on site is due to be intensive over the next few months as we coordinate with the Clients fit out contractors installation and commissioning of the Creamery commences.